Bathroom Remodel Cost in Maryland: What a Bathroom Remodel Costs in Anne Arundel & Howard County
By Anton Sergeev, Owner — MHIC #113057
How much does a bathroom remodel cost in Maryland?
A bathroom remodel in Anne Arundel and Howard County, Maryland typically costs $15,000–$30,000 installed by PRG Home Improvement. Cosmetic refresh, same footprint, tub or shower kept starts around $5,000; layout change or master bath with relocated plumbing and premium finishes reaches $90,000. Prices reviewed September 15, 2026.
Want a real number for your bathroom remodel?
Leave your name and phone. Anton — the owner, not a call center — calls back within one business day with a ballpark for your home.
Call 443-856-5379These are installed prices from PRG Home Improvement (MHIC #113057) for bathroom work in Anne Arundel and Howard County. They include labor, standard materials, bonded shower waterproofing, permit handling and inspections. Fixture and tile allowances are stated in every quote so an upgrade is a visible line, not a surprise.
The tier a bathroom lands in is decided by two things: whether the plumbing stays where it is, and whether the shower or tub area is rebuilt. Everything else is finish level.
Bathroom Remodeling cost by tier
Installed prices: labor, standard materials, permit handling and inspections. The right-hand column is what puts a project in that tier.
| Tier | Project | Installed cost | What puts a project here |
|---|---|---|---|
| Low | Cosmetic refresh, same footprint, tub or shower kept New vanity, top and faucet, toilet, lighting, mirror, accessories and paint; the tub or shower surround stays or is resurfaced. | $5,000–$12,000 |
|
| Typical | Full remodel in the same footprint with a new tile shower or tub Everything removed to the studs where the shower is, a new tiled shower or tub-shower with bonded waterproofing, tile floor, new vanity, fixtures, lighting and exhaust. | $15,000–$30,000 |
|
| High | Layout change or master bath with relocated plumbing and premium finishes Walls, drains or the toilet move; a curbless or large custom shower, freestanding tub, double vanity, heated floor, frameless glass and new circuits. | $35,000–$90,000 |
|
What a quote includes, and what is commonly left out
The gap between two quotes is usually in this list, not in the labor rate. Ask any contractor for both columns before comparing numbers.
Low tier — Cosmetic refresh, same footprint, tub or shower kept ($5,000–$12,000)
Included in a PRG quote
- Vanity, countertop, sink, faucet, toilet and accessories installed
- Lighting and exhaust fan replaced on existing circuits
- Paint, mirror, caulk and trim
Commonly excluded, quoted separately
- Tile work of any kind
- Any plumbing relocation or new electrical circuit
- Repairs to subfloor or framing found once the old vanity or toilet is out
Typical tier — Full remodel in the same footprint with a new tile shower or tub ($15,000–$30,000)
Included in a PRG quote
- Demolition and disposal, subfloor check and repair at the wet areas
- Bonded waterproofing membrane behind every wet wall and under the pan
- Shower or tub, valve, tile, niche, vanity, top, sink, toilet, lighting, fan, paint
- Permit and inspections when the county requires them for the plumbing or electrical scope
Commonly excluded, quoted separately
- Moving the toilet, shower drain or vanity plumbing
- Heated floors, frameless glass and freestanding tubs, quoted as add-ons
- Structural changes to walls, doors or windows
- Fixture and tile selections above the stated allowance
High tier — Layout change or master bath with relocated plumbing and premium finishes ($35,000–$90,000)
Included in a PRG quote
- Everything in the typical tier
- Plumbing relocation and new circuits under permit, with rough-in and final inspections
- Custom shower construction, curbless pan and linear drain where specified
- Heated floor system, frameless glass and premium fixtures at the stated allowance
Commonly excluded, quoted separately
- Moving plumbing stacks or venting through finished floors below
- Window replacement and exterior wall changes
- Steam generators and other specialty mechanical systems unless listed
Line items outside the tiers
| Item | Cost | When it applies |
|---|---|---|
| Heated tile floor | $1,500–$3,000 | Electric mat under the tile on its own circuit and thermostat. |
| Frameless glass shower enclosure | $800–$1,800 | Measured after tile; a separate line so the size and hardware are visible. |
| Tub-to-shower conversion | $3,500–$14,000 | Removing a tub and building a tiled shower in its footprint. Covered in more detail in the tub-to-shower conversion guide. |
Permits, inspections and HOA review in Anne Arundel and Howard County
Anne Arundel County
Anne Arundel County Office of Inspections and Permits
Building permit fee: $75–$300
- A cosmetic refresh (vanity, toilet, fixtures, paint) does not normally need a permit.
- Relocating plumbing, adding or moving a circuit, or changing framing requires a permit with plumbing and electrical sub-permits as applicable.
- Replacing a tub or shower valve in place is usually done under the plumbing sub-permit when the walls are open.
Howard County
Howard County Department of Inspections, Licenses and Permits (DILP)
Building permit fee: $100–$350
- Howard County requires a permit for any plumbing relocation, electrical circuit change or structural alteration; like-for-like fixture replacement does not need one.
- Plumbing and electrical inspections are scheduled at rough-in, before the walls are closed, and at final.
Inspection sequence
- Plumbing rough-in. When drains or supplies move: the inspector checks the new piping, venting and the shower pan test before waterproofing and tile cover it.
- Electrical rough-in. When circuits are added or moved: wiring for lighting, heated floor, fan and GFCI-protected outlets, inspected before drywall.
- Framing inspection. Only when walls, doors or windows change.
- Final inspection. Fixtures connected, GFCI and fan operation, and the finished work matching the permit.
HOA review
Interior bathroom work does not go through HOA architectural review. Condominium associations are the exception: many require notice for work that involves the building plumbing risers, proof of contractor insurance, and set working hours and elevator rules.
Full breakdown: sizes, materials, line items and hidden costs
The detail behind the tiers. Figures here are PRG's published prices for the same work and are reviewed on the same date as the tiers above.
How Much Does a Bathroom Remodel Cost by Bathroom Type?
The type of bathroom matters as much as the scope because the fixtures and square footage are different. These are typical Maryland prices for a standard remodel (new tile, new fixtures, same layout).
| Bathroom type | Typical size | Average cost in MD |
|---|---|---|
| Powder room (half bath, no shower/tub) | 15–25 sq ft | $4,500 – $7,500 |
| Half bath with shower | 25–35 sq ft | $8,000 – $13,000 |
| Full bath (tub/shower, vanity, toilet) | 35–50 sq ft | $14,000 – $22,000 |
| Jack-and-Jill bath | 50–70 sq ft | $18,000 – $28,000 |
| Master / primary bath | 70–120 sq ft | $25,000 – $45,000 |
| Luxury master with separate tub and walk-in shower | 100–200 sq ft | $45,000 – $90,000+ |
Bethesda and Chevy Chase prices run higher than this — Insite Remodeling lists $35,000–$75,000 for a standard hall bathroom in Bethesda and $75,000–$200,000 for a primary bath. In Anne Arundel and Howard Counties the same scopes typically run 20–35% less because of lower overhead and a less luxury-skewed buyer base.
Cost per Square Foot for a Bathroom Remodel in Maryland
Maryland bathroom remodels run $150 to $400 per square foot for a standard remodel, with most projects landing around $300/sq ft. Luxury remodels with custom tile, glass, and high-end fixtures can push past $500/sq ft.
| Bathroom size | Standard ($250/sq ft) | Mid-range ($325/sq ft) | High-end ($425/sq ft) |
|---|---|---|---|
| 40 sq ft | $10,000 | $13,000 | $17,000 |
| 60 sq ft | $15,000 | $19,500 | $25,500 |
| 80 sq ft | $20,000 | $26,000 | $34,000 |
| 100 sq ft | $25,000 | $32,500 | $42,500 |
| 150 sq ft | $37,500 | $48,750 | $63,750 |
Measure your bathroom and multiply. This will get you within ±15% of a real bid for most projects that keep the existing layout.
What Does Each Part of a Bathroom Remodel Cost?
Here's how the line items break down on a typical Maryland bathroom remodel. Prices are installed, including labor and standard materials.
Demolition and disposal
| Item | Cost in MD |
|---|---|
| Cosmetic demo (vanity, toilet, flooring only) | $300 – $800 |
| Full gut demo to studs and subfloor (35–50 sq ft bath) | $1,000 – $2,500 |
| Debris haul-off and dump fees | $400 – $800 |
Demo on a standard full bath is one to two days of work. Plaster-and-lath walls (common in pre-1950 Annapolis and Ellicott City homes) demo slower than drywall and add $300–$900 to this line.
Plumbing rough-in
| Item | Cost in MD |
|---|---|
| New shower/tub valve, same location | $600 – $1,200 |
| Tub-to-shower conversion rough-in (drain + valve) | $800 – $1,800 |
| Moving a toilet, sink, or shower drain | $1,500 – $3,500 |
| Re-piping bathroom supply lines (galvanized to PEX) | $500 – $1,800 |
Rough-in is the part of the budget that keeping your existing layout protects. Every fixture that stays where it is, is a rough-in line you don't pay.
Tub, shower, and shower pan
| Item | Installed cost in MD |
|---|---|
| New acrylic tub/shower combo (prefab) | $1,500 – $3,500 |
| Tub-to-shower conversion | $3,500 – $7,000 |
| Walk-in shower with prefab base + tile walls | $4,500 – $8,500 |
| Custom tile shower with mud-bed or foam pan | $6,500 – $12,000 |
| Curbless / zero-entry shower with linear drain | $8,000 – $14,000 |
| Freestanding soaking tub (tub only, plumbing extra) | $2,500 – $6,000 |
The shower is almost always the most expensive single element, and the part of it you'll never see — the waterproofing — is what decides whether it lasts twenty years or eight.
Shower waterproofing
| Item | Installed cost in MD |
|---|---|
| Bonded waterproof board, tub surround (3 walls) | $800 – $1,600 |
| Full walk-in shower envelope (walls, pan, curb, integrated drain) | $1,500 – $3,200 |
| Curbless shower waterproofing with linear drain integration | $2,200 – $4,000 |
Every shower I build gets a bonded waterproofing system — Schluter KERDI-BOARD, Wedi, GoBoard, or Laticrete Hydro Ban Board, depending on the job — where the board itself is the waterproof membrane and the drain connects mechanically to the walls as one sealed envelope. Never bare cement board behind tile, and never a roll-on membrane whose coverage nobody can verify once the tile is up. On a bid sheet this line looks optional, because Durock and a bucket of RedGard cost less. It isn't optional. Skipped or botched waterproofing is the #1 reason Maryland bathrooms get gutted a second time in 5–8 years, and the tear-out costs more than the whole line item did.
Vanity, countertop, and sink
| Item | Installed cost in MD |
|---|---|
| Stock 24"–30" single vanity (cabinet + top + sink) | $600 – $1,400 |
| Stock 36"–48" single vanity | $900 – $2,200 |
| Stock 60"–72" double vanity | $1,800 – $3,800 |
| Semi-custom or quartz-top vanity (any size) | $2,500 – $5,500 |
| Fully custom built-in vanity | $4,000 – $9,000+ |
Quartz tops in Maryland run $50–$80 per square foot installed. Marble runs $70–$190 per square foot. Stock vanities from the big-box stores are fine for most projects; custom is worth it when the wall length doesn't match a stock size or you want a furniture-style piece.
Toilet, fixtures, and trim
| Item | Installed cost |
|---|---|
| Standard two-piece toilet | $400 – $800 |
| Comfort-height / elongated upgrade | $600 – $1,200 |
| Macerating toilet (basement bathrooms with no drain below grade) | $1,400 – $2,200 |
| Faucet (vanity) | $200 – $600 |
| Shower valve and trim | $400 – $900 |
| Towel bars, robe hooks, paper holder set | $150 – $400 |
Maryland has a lot of older homes with basement bathrooms below the main sewer line. If yours is one of them, a macerating toilet (Saniflo or similar) costs more than a standard install but is worth every dollar versus the cost of breaking the slab.
Flooring
| Material | Installed cost per sq ft |
|---|---|
| Ceramic / porcelain tile | $10 – $20 |
| Luxury vinyl plank or tile (LVP/LVT) | $5 – $12 |
| Natural stone (marble, travertine, slate) | $20 – $50 |
| Heated floor (electric mat, add-on) | $12 – $20 |
| Sheet vinyl or linoleum | $4 – $10 |
For a 50 sq ft full bathroom, expect $500–$1,000 for the floor in vinyl, $800–$1,800 in standard porcelain tile, and $1,500–$3,000+ in natural stone.
Lighting, electrical, and exhaust
| Item | Installed cost |
|---|---|
| Vanity light fixture | $150 – $500 |
| Recessed can lights (per can, IC-rated for bathrooms) | $150 – $300 |
| New exhaust fan (properly vented to exterior) | $300 – $700 |
| GFCI outlet replacement | $150 – $250 |
| Full circuit upgrade or new dedicated circuit | $400 – $1,200 |
If you have a Maryland home built before about 1985 and you've never updated the bathroom electrical, plan on at least one GFCI upgrade and a properly vented exhaust fan. Builder-grade vent fans from the 70s and 80s were frequently terminated in the attic — that's not just a code issue, it's the root cause of attic mold in a lot of older Crofton, Severna Park, and Ellicott City homes.
What Percent of a Bathroom Remodel Is Labor?
Labor accounts for 40–60% of total cost on most Maryland bathroom remodels. On a $20,000 project, that's $8,000–$12,000 in labor and $8,000–$12,000 in materials. Custom tile work and complex plumbing push labor toward the high end; prefab fixtures and a stock vanity push it toward the low end.
The labor breakdown on a typical 50 sq ft full bathroom remodel looks roughly like this:
- Demolition and disposal: 1–2 days
- Plumbing rough-in (if any layout change): 1–2 days
- Electrical and fan: 0.5–1 day
- Framing / drywall / backer board / waterproofing: 2–3 days
- Tile setting (floor + shower): 3–5 days
- Trim, fixtures, vanity, finish: 2–3 days
That's why bathroom remodels in Maryland typically take 2 to 6 weeks from demo to final walk-through. See my full Maryland bathroom remodel timeline guide for a phase-by-phase schedule.
Hidden Costs in a Maryland Bathroom Remodel
This is the section the marketplace sites can't write because they're not the ones opening the wall. After 200+ Maryland bathrooms, here's what shows up on demo day on a regular basis:
| Hidden issue | Typical added cost |
|---|---|
| Rotten subfloor under tub or toilet flange | $400 – $1,500 |
| Cast iron drain stack cracked or corroded | $600 – $2,500 |
| Galvanized supply lines (common in pre-1965 homes) | $500 – $1,800 to re-pipe |
| Knob-and-tube wiring in older Annapolis / Edgewater / Severna Park homes | $1,000 – $3,500 |
| Plaster-and-lath walls instead of drywall (extra demo time) | $300 – $900 |
| Mold remediation behind tile or under tub | $800 – $3,500 |
| Out-of-square or out-of-plumb walls requiring framing correction | $400 – $1,200 |
| Asbestos floor tile or pipe wrap requiring abatement | $1,200 – $4,000 |
A good contractor builds a 10–15% contingency into your project budget for exactly these surprises. If you're getting a $15,000 estimate, plan for $17,000 in cash available. I write all my contracts with a defined change-order process so if something shows up behind the wall, you see the cost, you approve it, and the work moves forward without surprises at the end.
What the Cost Aggregators Don't Tell You
Type "bathroom remodel cost" into a search engine and the top results are national aggregator sites quoting national averages. Two problems with that. First, a national average blends Mississippi labor rates with San Francisco ones — it doesn't price a bathroom in Crofton or Columbia. Second, and more important: those sites price the visible scope. They can't tell you what a low bid quietly leaves out, because they've never carried one.
When two bids for the same bathroom are $6,000 apart, the cheaper one is usually missing one or more of these:
- A real waterproofing system. Tile straight over cement board, or a single thin coat of roll-on membrane, instead of a bonded system like Schluter, Wedi, or GoBoard. Invisible on day one, catastrophic by year eight.
- Permits. "We don't need one for this" saves the fee and the inspection — and leaves you holding an unpermitted plumbing alteration at resale.
- An exhaust fan actually ducted outside. Terminating the vent in the attic is faster and invisible. It's also how attic mold starts.
- Demo disposal, floor leveling, and the contingency process. If the bid doesn't say who pays when the subfloor comes up rotten, you do — at a price negotiated mid-project when you can't walk away.
Before comparing totals, compare scopes line by line. A lower number for a narrower scope isn't a better price — it's a different, smaller project wearing the same name.
What's the ROI on a Maryland Bathroom Remodel?
According to the 2025 Cost vs. Value Report from Remodeling Magazine and Zonda, midrange bathroom remodels nationally return 74–80% of their cost at resale — among the highest ROI of any interior renovation. Upscale and luxury remodels typically return 42–55%.
| Remodel scope | National ROI (2025 Cost vs. Value) | Example: $20,000 project |
|---|---|---|
| Minor / cosmetic refresh | 70–85% | Adds ~$15,000 in resale value |
| Midrange standard remodel | 74–80% | Adds ~$16,000 in resale value |
| Universal design / accessibility | 60–65% | Adds ~$12,500 in resale value |
| Upscale / luxury remodel | 42–55% | Adds ~$9,500 in resale value |
The Mid-Atlantic region (including Maryland) tends to track close to the national average. In strong submarkets like Severna Park, Crofton, Annapolis, Davidsonville, and Clarksville, return on a midrange remodel can hit the top of the range because buyer expectations are high and an outdated bathroom is a deal-breaker for a lot of buyers.
The takeaway: midrange beats luxury for ROI. Unless you're remodeling for personal enjoyment in a home you plan to keep long-term, don't overbuild beyond your neighborhood's comp ceiling.
How to Save Money on a Bathroom Remodel in Maryland
- Keep the layout. Moving the toilet, shower drain, or sink adds $1,500–$3,500 to the project before tile is even back on the wall. Unless the existing layout is unusable, leave it.
- Mid-range materials, not luxury. Quartz beats marble for resale ROI and durability. Stock vanities from a real cabinet supplier (not particle-board big-box) beat custom for most rooms.
- DIY the demo, paint, and fixture install. A homeowner can reasonably save $1,500–$3,000 by handling demolition, painting, and toilet/vanity install themselves and leaving the tile, plumbing, and waterproofing to a pro.
- Bundle with another project. If you're already pulling permits for a kitchen or basement, adding a bathroom to the same job saves on permit fees and contractor mobilization.
- Look for utility rebates. BGE offers rebates on certain WaterSense fixtures and high-efficiency exhaust fans through its smart energy program. The Maryland Energy Administration (MEA) has appliance and efficiency incentives that occasionally apply to bathroom upgrades — check energy.maryland.gov for current programs.
- Hire an owner-operator contractor for smaller projects. A solo licensed contractor like me has lower overhead than a design-build firm — typically 15–25% less on the same scope of work because there's no project manager, no in-house designer, and no showroom to pay for. The trade-off is a smaller schedule of available start dates.
How to Finance a Bathroom Remodel in Maryland
Most Maryland homeowners pay for a bathroom remodel through one of four routes:
- Home equity line of credit (HELOC). If you have equity in your home, this is usually the cheapest financing. Interest is variable but typically lower than personal loans, and interest may be tax-deductible if the funds are used for home improvement (consult your tax preparer).
- Cash-out refinance. Worth considering if current mortgage rates are at or below your existing rate, otherwise a HELOC is usually cheaper.
- Home improvement loan (unsecured personal loan). Faster to close than a HELOC, fixed rate, but higher interest. Good option if you don't have equity yet.
- FHA 203(k) renovation loan. If you're buying a home that needs work, a 203(k) lets you finance the remodel into the purchase mortgage. Useful for distressed properties.
I don't take credit cards for full projects (the processing fees would be passed back to you anyway), but most clients pay by check or ACH on a milestone schedule: deposit, mid-project, and final upon completion.
Get a real number for your bathroom remodel
The tiers above are how PRG scopes bathroom remodel projects, and the ranges are our installed prices. The number for your home depends on what is already there and what you choose. Describe the project to the AI estimator for a range now, or book an in-home estimate for a line-item quote.
Describe your project to the AI estimator →Bathroom Remodeling cost questions
- How much does a bathroom remodel cost in Maryland?
- In Anne Arundel and Howard County, a full bathroom remodel in the same footprint with a new tiled shower typically costs $15,000 to $30,000 installed by PRG. A cosmetic refresh that keeps the tub or shower starts around $5,000; a layout change or master bath with relocated plumbing and premium finishes reaches $90,000. Prices reviewed September 15, 2026.
- What is included in a bathroom remodel quote from PRG?
- Demolition, subfloor repair at the wet areas, bonded waterproofing behind every wet wall and under the pan, the shower or tub with valve and tile, vanity and top, toilet, lighting, exhaust fan, paint, and the permit and inspections when the scope needs them. Fixture and tile allowances are stated in the quote.
- Do I need a permit to remodel a bathroom in Anne Arundel or Howard County?
- Not for a cosmetic refresh. Yes in both counties once plumbing is relocated, a circuit is added or moved, or framing changes. Anne Arundel County runs permits through the Office of Inspections and Permits and Howard County through DILP; PRG pulls the permit and schedules the rough-in and final inspections.
- What moves a bathroom from the typical tier to the high tier?
- Moving plumbing is the biggest step, because it opens the floor and brings a plumbing permit. After that it is the shower itself: curbless pans, linear drains, benches and large-format tile add labor, and heated floors, freestanding tubs, double vanities and frameless glass add material.
- Why does PRG insist on a bonded waterproofing membrane?
- Cement board alone is not waterproof, and Maryland humidity punishes a shower that relies on it. Schluter, Wedi or GoBoard behind the tile is included at the typical tier rather than offered as an upgrade because it is the difference between a shower that lasts and one that leaks into the framing.
- How do I get a real number for my bathroom?
- Describe the bathroom to the AI project estimator for a range now, or call 443-856-5379 for an in-home estimate. The owner checks the existing plumbing and framing and writes a line-item quote with stated allowances.
Who Will Run Your Project
Anton Sergeev — Owner & Lead Craftsman
- MHIC #113057 — licensed & insured in Maryland. Verify license →
- Hands-on in construction since 2010 — electrician, property management, then custom home builders. MHIC licensed since 2017.
- Anton personally performs or supervises the critical finish work on every project — you work with the owner from estimate to final walkthrough.
- Trusted, licensed subcontractors are brought in only for specialized trades such as electrical, plumbing, HVAC, and concrete.
- 1-year workmanship warranty on our labor, with manufacturer warranties on materials passed through to you.
"Anton has done many jobs for us, including bathroom remodel, cabinet installation, built-ins, painting, fan and light fixture installation. I cannot say enough about him! He is communicative, creative, neat, and completes projects in a timely manner. I can't wait for him to do more projects for us!"
— Kelly Aziz, Odenton, MD · Verified Google review