Kitchen Remodel Cost in Maryland: What a Kitchen Remodel Costs in Anne Arundel & Howard County
By Anton Sergeev, Owner — MHIC #113057
How much does a kitchen remodel cost in Maryland?
A kitchen remodel in Anne Arundel and Howard County, Maryland typically costs $30,000–$60,000 installed by PRG Home Improvement. Refresh: cabinets kept, new counters, backsplash, sink, lighting and paint starts around $15,000; layout change with wall removal, island with utilities and custom cabinetry reaches $100,000. Prices reviewed September 15, 2026.
Want a real number for your kitchen remodel?
Leave your name and phone. Anton — the owner, not a call center — calls back within one business day with a ballpark for your home.
Call 443-856-5379These are installed prices from PRG Home Improvement (MHIC #113057), based in Gambrills, for kitchen work in Anne Arundel and Howard County: Crofton, Odenton, Severna Park, Annapolis, Columbia, Ellicott City and the communities between. They cover labor, cabinets and counters at a stated allowance, electrical brought to code, permit handling and inspections.
A kitchen lands in a tier based on whether the cabinets are replaced and whether the layout changes. Finish level moves the number within a tier; walls and plumbing move it between tiers.
Kitchen Remodeling cost by tier
Installed prices: labor, standard materials, permit handling and inspections. The right-hand column is what puts a project in that tier.
| Tier | Project | Installed cost | What puts a project here |
|---|---|---|---|
| Low | Refresh: cabinets kept, new counters, backsplash, sink, lighting and paint The cabinet boxes stay (painted or refaced), with new countertops, tile backsplash, sink and faucet, lighting and paint. | $15,000–$25,000 |
|
| Typical | Full replacement in the same layout New semi-custom cabinets, quartz counters, tile backsplash, new flooring, plumbing in place, electrical brought to code, new lighting. | $30,000–$60,000 |
|
| High | Layout change with wall removal, island with utilities and custom cabinetry A wall comes out with an engineered beam, the sink or range moves, an island gets plumbing and electrical, and cabinetry is custom. | $65,000–$100,000 |
|
What a quote includes, and what is commonly left out
The gap between two quotes is usually in this list, not in the labor rate. Ask any contractor for both columns before comparing numbers.
Low tier — Refresh: cabinets kept, new counters, backsplash, sink, lighting and paint ($15,000–$25,000)
Included in a PRG quote
- Countertop template and installation, tile backsplash, sink, faucet and disposal
- Cabinet painting or refacing with new hardware
- Lighting fixtures and paint
Commonly excluded, quoted separately
- New cabinets or any change to the cabinet layout
- Appliances and appliance installation beyond reconnecting existing units
- Electrical upgrades to bring circuits to current code
- Flooring
Typical tier — Full replacement in the same layout ($30,000–$60,000)
Included in a PRG quote
- Demolition and disposal, drywall repair, cabinets and installation at the stated allowance
- Counters, backsplash, sink, faucet, disposal and flooring
- Electrical permit and the circuits and lighting the code requires, appliance hookups
- Permit application and all inspections
Commonly excluded, quoted separately
- Appliances themselves, unless purchased through the quote
- Moving the sink, range, gas line or any wall
- Custom or inset cabinetry above the allowance
- Flooring beyond the kitchen into adjoining rooms
High tier — Layout change with wall removal, island with utilities and custom cabinetry ($65,000–$100,000)
Included in a PRG quote
- Everything in the typical tier
- Engineered beam design and installation, temporary support and framing inspection
- Plumbing, gas and electrical relocation under permit with rough-in and final inspections
- Custom cabinetry and island construction
Commonly excluded, quoted separately
- Additions that change the exterior footprint
- Window and exterior door replacement unless listed
- Appliances, unless purchased through the quote
Line items outside the tiers
| Item | Cost | When it applies |
|---|---|---|
| Engineered beam for a load-bearing wall removal | $5,000–$15,000 | Engineer's calculation and stamped detail, plus the steel or LVL beam and posts down to bearing. |
Permits, inspections and HOA review in Anne Arundel and Howard County
Anne Arundel County
Anne Arundel County Office of Inspections and Permits
Building permit fee: $200–$600
- A cosmetic refresh (counters, backsplash, paint, doors) does not normally need a permit.
- New or relocated circuits, relocated plumbing or gas, and any wall removal require a permit with electrical, plumbing and mechanical sub-permits as applicable.
- Replacing cabinets in the same layout still usually brings an electrical permit, because current code requires dedicated appliance circuits and GFCI protection that older kitchens lack.
Howard County
Howard County Department of Inspections, Licenses and Permits (DILP)
Building permit fee: $200–$600
- Howard County requires a permit for electrical, plumbing, gas or structural changes; like-for-like replacement of fixtures does not need one.
- A load-bearing wall removal needs stamped engineering with the permit application.
Inspection sequence
- Framing inspection. Only for wall removal: the beam, posts and bearing path are checked against the engineer's detail before drywall.
- Electrical rough-in. New circuits, appliance runs and lighting wiring inspected before the walls and ceiling are closed.
- Plumbing and gas rough-in. When the sink, dishwasher, range or gas line moves: piping and venting inspected open, and a gas pressure test.
- Final inspection. GFCI and circuit checks, appliance connections, gas final, and the finished kitchen matching the permit.
HOA review
Interior kitchen work does not go through HOA architectural review in Anne Arundel or Howard County communities. Condominium and townhome associations may require notice for plumbing or gas work that touches shared risers, proof of insurance, and working-hour rules.
Full breakdown: sizes, materials, line items and hidden costs
The detail behind the tiers. Figures here are PRG's published prices for the same work and are reviewed on the same date as the tiers above.
Cost per Square Foot for a Kitchen Remodel in Maryland
Kitchen remodels in Maryland run $150 to $400 per square foot, with most mid-range projects landing around $250–$350/sq ft. A refresh scope sits near the bottom of that band; custom work with layout changes sits above it.
| Kitchen size | Refresh (~$150/sq ft) | Mid-range (~$300/sq ft) | Custom (~$400/sq ft) |
|---|---|---|---|
| 100 sq ft (small / galley) | $15,000 | $30,000 | $40,000 |
| 150 sq ft (typical) | $22,500 | $45,000 | $60,000 |
| 200 sq ft (large) | $30,000 | $60,000 | $80,000 |
| 250 sq ft (open concept) | $37,500 | $75,000 | $100,000 |
Measure your kitchen and multiply — it gets you within striking distance of a real bid for a same-layout project. Layout changes break the per-square-foot math, because moving plumbing and opening walls doesn't scale with area.
What Does Each Part of a Kitchen Remodel Cost?
Here's how the line items break down on a typical Maryland kitchen remodel. Prices are installed, including labor and standard materials.
Demolition and disposal
| Item | Cost in MD |
|---|---|
| Cosmetic demo (counters, backsplash, flooring only) | $300 – $900 |
| Full kitchen demo (cabinets, soffits, flooring, drywall as needed) | $1,500 – $3,500 |
| Debris haul-off and dump fees | $400 – $800 |
Cabinets
Cabinets are the biggest single line — typically 30–40% of total project cost.
| Cabinet tier | Installed cost (typical 150 sq ft kitchen) |
|---|---|
| Cabinet refacing (new doors/drawer fronts on existing boxes) | $9,000 – $18,000 |
| Stock cabinets (standard sizes, big-box lines) | $6,000 – $12,000 |
| Semi-custom cabinets (made to order, wider size/finish range) | $12,000 – $25,000 |
| Custom cabinets (built to spec by a cabinet maker) | $25,000 – $50,000+ |
Semi-custom is the sweet spot for most mid-range Maryland remodels — significantly better boxes, drawer hardware, and fit than stock, without the 3–5x premium of full custom. Custom earns its price when walls are out of square, ceilings are high, or you want a furniture-grade look.
Countertops
| Material | Installed cost per sq ft |
|---|---|
| Laminate | $25 – $45 |
| Butcher block | $35 – $75 |
| Granite | $45 – $85 |
| Quartz | $50 – $80 |
| Quartzite or marble | $80 – $150 |
A typical kitchen carries 40–55 sq ft of counter, so quartz — the most popular choice in this market for good reason — runs $2,500–$4,500 installed. Granite prices similarly with more slab-to-slab variation; quartzite and marble are premium materials that also demand more care.
Plumbing and gas
| Item | Installed cost |
|---|---|
| Sink and faucet swap (same location) | $400 – $900 |
| Moving the sink (re-routing drain and supply) | $2,000 – $5,000 |
| Gas line for a relocated or new gas range | $1,500 – $3,000 |
| Pot filler at the range | $600 – $1,200 |
| Dishwasher or ice-maker line | $200 – $500 |
Electrical and lighting
| Item | Installed cost |
|---|---|
| Recessed can lights (per can) | $150 – $300 |
| Under-cabinet LED lighting | $300 – $900 |
| New dedicated circuit (code requires two 20A small-appliance circuits) | $400 – $1,200 |
| Island receptacle with floor run | $300 – $700 |
| Panel upgrade from 100A to 200A (if required) | $1,800 – $3,500 |
Kitchens built before the 1990s frequently need electrical brought to current code once the walls are open — an inspector will require it, and a bid that doesn't mention it hasn't priced it.
Flooring and backsplash
| Item | Installed cost |
|---|---|
| Luxury vinyl plank (LVP) | $5 – $12 per sq ft |
| Ceramic / porcelain tile | $10 – $20 per sq ft |
| Hardwood (new or lace-in to existing) | $12 – $25 per sq ft |
| Ceramic subway backsplash | $800 – $2,000 |
| Stone, mosaic, or full-height backsplash | $1,500 – $4,500 |
Appliances
Appliances range from $3,000 for a basic package to $25,000+ for professional-grade. Mid-range packages from brands like KitchenAid, Bosch, or GE Café typically run $6,000–$12,000 for a full suite. Most clients buy appliances themselves during holiday-weekend sales and I install them — that's the cheapest route, and it keeps a retailer markup out of the project.
Layout changes and structural work
Moving the sink requires re-routing drain lines — add $2,000–$5,000 depending on complexity. Moving a gas range involves gas line work — add $1,500–$3,000. Opening a wall between the kitchen and dining room adds $5,000–$15,000 if structural work is required — a load-bearing wall needs an engineered beam, permits, and inspections, which is most of that number. Adding an island with electrical runs $4,000–$12,000 installed depending on size and cabinetry tier; plumbing in the island adds the sink-move cost on top.
What Percent of a Kitchen Remodel Is Labor?
Labor accounts for 35–50% of total cost on most Maryland kitchen remodels — lower than a bathroom's share, because cabinets, counters, and appliances are materials-heavy line items. On a $45,000 mid-range project, that's roughly $16,000–$22,000 in labor across demo, carpentry, cabinet install, tile, plumbing, electrical, and paint. Custom tile, layout changes, and structural work push labor toward the high end.
Hidden Costs in a Maryland Kitchen Remodel
This is the section the marketplace sites can't write, because they're not the ones opening the walls. Here's what regularly shows up on demo day in Anne Arundel and Howard County kitchens:
| Hidden issue | Typical added cost |
|---|---|
| Floors out of level (cabinets and counters need a flat plane) | $500 – $1,500 |
| Subfloor rot at the sink base or dishwasher | $400 – $1,500 |
| Galvanized supply lines (pre-1965 homes) | $500 – $1,800 to re-pipe |
| Knob-and-tube or cloth-wrapped wiring in older Annapolis / Severna Park homes | $1,000 – $3,500 |
| Aluminum branch wiring needing remediation (late-1960s–70s homes) | $800 – $2,000 |
| Ducts, drains, or gas lines inside a wall planned for removal | $800 – $2,500 to re-route |
| Asbestos floor tile under existing flooring | $1,200 – $4,000 for abatement |
| Panel at capacity, no room for required new circuits | $1,800 – $3,500 to upgrade |
A good contractor builds a 10–15% contingency into the budget for exactly these. If your estimate is $45,000, plan for $50,000 in cash available. I write every contract with a defined change-order process — if something shows up behind the wall, you see the cost, you approve it, and the work moves forward without a surprise invoice at the end.
What the Cost Aggregators Don't Tell You
National cost sites quote national averages, which blend labor markets that have nothing to do with Anne Arundel or Howard County. The bigger problem is what they can't see: how kitchen bids are actually built. When two quotes for the same kitchen are $15,000 apart, check for these before assuming you found a deal:
- Cabinet allowances. A bid with a low "cabinet allowance" isn't cheaper — it's deferring the real cabinet price to a selection meeting after you've signed.
- Appliances and counters excluded. "Starting at" numbers frequently cover labor and boxes only. Confirm what's an allowance, what's excluded, and what's actually priced.
- Electrical code work missing. If the panel, circuits, and GFCI/AFCI requirements aren't in the bid on an older house, they'll be a change order later — the inspector doesn't negotiate.
- Permits skipped. Unpermitted plumbing, electrical, or structural work saves the low bidder a fee and an inspection, and leaves you explaining it at resale.
Compare scope line by line, not totals. A lower number for a narrower scope is a different, smaller project wearing the same name.
What's the ROI on a Kitchen Remodel in Maryland?
Kitchen remodels consistently rank among the highest-ROI home improvements in the Mid-Atlantic region. A mid-range kitchen remodel in Maryland typically recoups 60–75% of its cost at resale. Updated kitchens are one of the top factors buyers consider — in competitive markets like Annapolis, Columbia, and Ellicott City, an outdated kitchen can meaningfully affect your sale price and time on market.
How to Save Money on a Kitchen Remodel in Maryland
- Keep the layout. Every fixture that stays put is $1,500–$5,000 of plumbing, gas, and electrical relocation you don't pay. Unless the layout genuinely doesn't work, leave the sink and range where they are.
- Reface instead of replace if your boxes are sound. $9,000–$18,000 for refacing versus $12,000–$25,000+ for new semi-custom cabinets — with most of the visual impact.
- Semi-custom cabinets, quartz counters. The mid-tier combination that holds up and sells — full custom and exotic stone rarely return their premium at resale.
- Buy your own appliances on sale, have them installed as part of the project. Holiday-weekend appliance pricing beats any allowance a contractor can offer.
- Bundle with other work. Sharing permits and mobilization with a bathroom or basement project on the same job saves real money.
- Hire an owner-operator licensed contractor. Design-build firms with showrooms and project managers run 15–25% higher on the same scope. The trade-off is a smaller schedule of available start dates.
Get a real number for your kitchen remodel
The tiers above are how PRG scopes kitchen remodel projects, and the ranges are our installed prices. The number for your home depends on what is already there and what you choose. Describe the project to the AI estimator for a range now, or book an in-home estimate for a line-item quote.
Describe your project to the AI estimator →Kitchen Remodeling cost questions
- How much does a kitchen remodel cost in Maryland?
- A full kitchen replacement in the same layout, with semi-custom cabinets, quartz counters, new flooring and electrical brought to code, typically costs $30,000 to $60,000 installed by PRG in Anne Arundel and Howard County. A refresh that keeps the cabinet boxes starts around $15,000; a layout change with a wall removal, relocated plumbing and custom cabinetry reaches $100,000. Prices reviewed September 15, 2026.
- What is included in a kitchen remodel quote from PRG?
- Demolition, cabinets and installation at a stated allowance, counters, backsplash, sink and faucet, flooring, the electrical circuits and lighting current code requires, appliance hookups, and the permit and inspections. Appliances, layout changes and cabinetry above the allowance are separate lines.
- Do I need a permit for a kitchen remodel in Anne Arundel or Howard County?
- Not for counters, backsplash and paint. Yes for new or relocated circuits, relocated plumbing or gas, and any wall removal. Most full cabinet replacements bring an electrical permit because older kitchens lack the dedicated circuits and GFCI protection the code now requires. PRG pulls the permit through the Anne Arundel County Office of Inspections and Permits or Howard County DILP.
- What does removing a wall add to a kitchen remodel?
- An engineer sizes a beam, the framing is temporarily supported while the beam and posts go in, and the county inspects the framing before drywall. Relocating the sink or range usually comes with it, which adds plumbing or gas permits. Together these are what move a kitchen into the high tier.
- Is kitchen remodel pricing different in Howard County than in Anne Arundel County?
- No. The tiers and what they include are the same in Columbia, Ellicott City, Fulton, Clarksville and the rest of Howard County as in Crofton, Odenton or Annapolis. What changes is the permit: it runs through Howard County DILP instead of the Anne Arundel County office, and Howard County requires stamped engineering for a load-bearing wall removal.
- How do I get a real number for my kitchen?
- Describe the kitchen to the AI project estimator for a range now, or call 443-856-5379 for an in-home estimate. The owner measures, checks the electrical panel and plumbing, and writes a line-item quote with stated allowances.
Who Will Run Your Project
Anton Sergeev — Owner & Lead Craftsman
- MHIC #113057 — licensed & insured in Maryland. Verify license →
- Hands-on in construction since 2010 — electrician, property management, then custom home builders. MHIC licensed since 2017.
- Anton personally performs or supervises the critical finish work on every project — you work with the owner from estimate to final walkthrough.
- Trusted, licensed subcontractors are brought in only for specialized trades such as electrical, plumbing, HVAC, and concrete.
- 1-year workmanship warranty on our labor, with manufacturer warranties on materials passed through to you.
"Anton was very professional and offered a reasonable price for a full bathroom and kitchen demolition and renovation. He worked closely with me to achieve the aesthetic that I envisioned and even went as far as to pick up larger items from Home Depot/Lowes on my behalf. I love the way my new kitchen and bathroom look! Would highly recommend Anton and PRG Contractors!"
— Leigha Carryl, Annapolis, MD · Verified Google review